The Village of Waterford, Virginia
   A National Historic Landmark

photos of Waterford VA Our annual fair is over 50 years old Waterford gardening activities and natural resources What we do on July 4th Waterford's history About our town
about the village
Visiting historic Waterford
How to get to Waterford
History of Waterford and Loudoun County
About the fair including photos
Village and historical maps
articles and news
Information for residents
site index
about the Foundation
about the WCA
1PLs - Personal loan from 1000 to 35000 dollars

Go to the Foundation web site Foundation events About the citizens' association About the citizens' association Join the WCA web pages for members only
Traffic home page
Bury wires & traffic calming home page

This document reviews the scope of services that the Loudoun County contractor will be undertaking.

Preliminary Engineering Services to "Bury the Wires and Tame the Traffic"
Waterford, VA

SCOPE OF SERVICES (Loudoun County RFP QQ-00963)

Introduction: The Consultant will provide professional engineering services to conduct investigations, perform preliminary engineering studies, and develop concept designs to "tame the traffic," bury overhead utility wires, and improve drainage in Waterford, while preserving and enhancing the historic character of the Village. Project Goal: To develop a set of practical, preliminary solutions that will provide the Village of Waterford with a master plan to take the next step in the planning and design process.

Kimley-Horn Team:

  • Kimley-Horn and Associates (Lead/Traffic/Roadway)
  • Walkable Communities (Planning)
  • B2E Consulting Engineers (Electrical)
  • William H. Gordon Associates (Civil)
  • Williamsburg Environmental Group (Environmental)
  • The Louis Berger Group (Historical)

Background:

  • National Historic Landmark District, Virginia Landmark Historic District, and a Loudoun County Historic District
  • Challenges with traffic growth in Loudoun County
  • Desire to relocate overhead utility wires and improve storm drainage
  • Need for an overall master plan to take to the next steps in funding process

Study Tasks:

Task 1 Data Collection: Mapping/GIS, traffic, utilities, stormwater, roadway, lighting environmental, historical resources, etc.

Task 2 Engineering Studies:

  • Traffic Calming Alternatives
  • Electrical/Telephone Utilities Alternatives
  • Utility Stormwater Drainage Alternatives
  • Roadway Alignment Alternatives
  • Environmental and historic resources considerations / review

Task 3 Preliminary Master Plan Concepts

Task 4 Design Workshop with Village Representatives, County, VDOT

Task 5 Public Presentation Meeting

Task 6 Final Design Alternatives Report - Master Plan Concepts

Schedule:

  • Feb. - Mar 03 Kick-Off Meeting / Public Meetings / Data Collection / Engineering Studies
  • Apr - Jun 03 Concept Designs and Design Workshop / Opinions of Construction Cost
  • Jul 03 Public Presentation Meeting and Final Report

 

 Top of page

 

 

traffic, bury wires, traffic calming, roads, esthetics, burying overhead wires, automobile spped reduction, waterford, va, virginia, waterford va, historic towns, loudoun county, civil war towns, villages, village, national historic landmark

 

- 11/20/2004

www.waterfordva-wca.org © 2023